Update as of February 2nd: Our move will be delayed 1-2 weeks due to need to reschedule move of our radiographic unit because all permits won’t be ready on time. I will let you know our new move date very soon.
Construction should be 99% complete this week, completely done by next week. Our tentative move date is February 12th. Our digital radiographs will be down on the 8-10th as it is being moved. Lab equipment is being moved on the 13th.
So on the 13th, we will be starting to see patients in our new building.
We are still going to have boarding in our current building, but we are going to take advantage of the slower time of year to do some much-needed rehab on our kennels. That means any pets that require boarding will board at our new building until repairs and painting are complete. Luckily we will have plenty of exercise space in our future rehabilitation area.
Unfortunately, it looks like our signs may not be ready in time, so banners will have to do in the meantime. We will send out a mailing to let you know all the details, but hours, phone number, will be the same. Just a new address and brand spanking new facilities.
Pictures on our new building blog are up to date as of last week. Please check them out.
Let me know if you have any questions or concerns.